Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Clock ticking for Orkney wind farm planning request

Wind turbines on Orkney.
Faray wind farm planning permission decision now with Scottish government.

Orkney Islands Council (OIC) says “time is running out” for planning permission to be granted for its wind farm project on Faray with a resulting interconnector supplying energy to the mainland generating a potential £6 million annual windfall to the county.

The Faray wind farm is the last piece in the interconnector’s turbine jigsaw with planning permission having been granted for similar projects at Quanterness and Hoy last year.

Decision is ‘critically important’

But with the clock rapidly ticking down before a decision is required in October, OIC has written to the Scottish Government stressing the “critical importance” of a decision surrounding planning permission.

The proposed six-turbine wind farm on Faray is the last part of Orkney’s community wind farm project with the Scottish government calling in the application in September 2021.

Orkney wind farm turbines.
Photomontage of Faray planned wind farm. Supplied by Orkney Islands Council.

Any decision has yet to be determined but the Foray link is a crucial part of electricity generator regulator Ofgem’s “needs case” for a new interconnector between Orkney and the Scottish mainland.

In September 2019 Ofgem published its final decision on the needs case for a new interconnector, setting out that planning permission for 135MW of new generation was required.

This would need to be signed up to a grid connection agreement, as well as pass a financial audit before the end of 2021 in order to trigger the interconnector.

New electricity link from Orkney to mainland could be worth nearly £1.5bn to Scottish economy

This was later extended to 2022 as a result of the delays experienced due to the pandemic.

An independent economic report found a new electricity transmission link between Orkney and the Scottish Mainland could be worth nearly £1.5 billion to the Scottish economy.

In order for Orkney to meet the needs case, the council took a ‘developer approach’, working on proposals for the three 28.8MW sites, with six 150m high turbines on each.

Leader of Orkney Island Council James Stockan told the Press and Journal: “The application has been with the Scottish government for a considerable amount of time and so much opportunity in future hangs on this.”

There are currently around 110MW of projects consented – including Orkney’s community wind farm project sites at Hoy and Quanterness.

Mr Stockan continued: “The only project which has potential to fill the remaining gap and trigger the cable before the end of year deadline is the Faray project – without it the cable simply will not happen.

Orkney Council Leader James Stockan.
Orkney Council Leader James Stockan.

“In their previous determinations on Quanterness and Hoy, Scottish Ministers quite rightly highlighted the interconnector as being a key factor in their decision – and gave substantial weight to this.

“These projects were successful in the latest contract for difference (CfD) auction round four, which provides a guaranteed price for the electricity produced for 15 years and also contributes to the Ofgem needs case”

We need a decision before October”

– Orkney Council leader James Stockan

“However, the timescales are now tight – the project has been with the Scottish government for close to a year now and we have therefore written to them to ask for urgent action.

“We need a decision on these projects before October – otherwise the future of these critical projects could be in jeopardy.”

The Scottish government noted the reporter is “still working on his report” with recommendations to ministers, who will make the final decision on the development.

Holyrood added as “the case is live” it would not be appropriate to comment on the merits of the proposal at this stage.