Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

New £333million AECC to be approved again due to Queen’s cousin

Post Thumbnail

Councillors are being asked to reapprove work to create the new £333million Aberdeen Exhibition and Conference Centre due to a complex legal battle between the local authority and the Queen’s cousin.

The city’s planning development management committee will meet next Thursday to debate planning permission in principle for the massive scheme – in a bid to prevent a potential loss of nearly £1million in developer contributions.

Henry Boot Developments Ltd commenced work last summer to create the new AECC on the former site of the Rowett Research Institute at Bucksburn.

Alongside the 12,500 capacity events venue, two hotels and a green energy plant are also included with completion expected in 2019.

Aberdeen and Aberdeenshire councils were dealt a blow last year when the Duke of Fife – whose company is behind the Chapelton of Elsick scheme near Newtonhill – successfully challenged an £8million developer contribution demand.

His firm had been asked to hand over the money to the strategic transport fund as part of its planning consent – but Court of Session judges reduced the bill to just £287,000.

The Strategic Development Planning Authority (SDPA) – which comprises representatives from both authorities – has agreed to appeal against the decision to the Supreme Court.

A report to councillors stated: “At the time of writing, demolition works at the site are substantively complete and extensive earthworks are underway.

“In the absence of the STF Supplementary Guidance, it was agreed by the SDPA and both Aberdeen City and Aberdeenshire Councils that developers may agree with the council an alternative “strategic transport infrastructure contribution”, for transport interventions.

“[This is] directly related to the transport impact of the development, the mechanism of which shall be on a case-by-case basis.

Prior to the Duke’s legal victory, Aberdeen City Council had estimated it would gain a contribution of more than £1.3million from the AECC development. However, this could be reduced to £353,500.

Committee chair Ramsay Milne said it was “disappointing” the project had to be resubmitted due to the legal case.

Responding to the impending legal action, the Duke of Fife said: “We have been notified of the decision of The Supreme Court to consider the appeal and are surprised.

“The Inner House of the Court of Session was clear in its judgement on the case and in refusing leave to appeal. We remain very confident in the strength of our case, but are disappointed we have to go through the argument all over again.”