Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

‘Banff Harbour could be finished’: Fears for port as repairs are abandoned amid contract dispute

The work has ground to a halt. Inset, the damage when part of the pier crashed into the sea in 2017

Battered Banff Harbour “could be finished” as major repairs to the historic port hang in the balance amid a dispute between the council and contractors.

Parts of a crumbling wall came loose and crashed into the sea in the spring of 2017 following freak storms, and long-awaited restoration work got under way in January.

Aberdeenshire Council appointed Lochshell Ltd to reinstate the damaged railway jetty, which was once where trains would arrive at the port to pick up goods.

The firm was also tasked with strengthening the east pier as part of the deal.

But now workers have downed tools after discovering “unexpected ground conditions”.

And harbour users fear that, unless the wall is repaired by the time winter gales sweep in, then the port could end up suffering irreparable damage.

Heavy machinery has been sitting idle at the harbour in recent days. Picture by Paul Glendell

What does contractor say?

Lochshell, which is based just outside Wick, told us that work ground to a halt when it emerged the job was more complex than first expected.

A statement from the firm said: “Lochshell Engineering is currently awaiting updated contract design documents from Aberdeenshire Council due to unexpected ground conditions found on site.

“Once received, this will then allow works to resume and progress to completion at Banff Harbour.

“We fully support the project and improvements being made and invested in by Aberdeenshire Council, and are keen to deliver the works which will return the harbour to the local community as soon as practicable.”

The silent scene at Banff Harbour as the scheme remains at a standstill – 

Council ‘profoundly disappointed’

Aberdeenshire Council has confirmed that the expected completion date of early September will not be met, but stressed that officials are doing all they can to get the scheme back on track.

Alan Wood, director of infrastructure services said: “Works at Banff Harbour have been suspended while contractual discussions are held.

“We are profoundly disappointed by this delay in the project and I would like to reassure harbour users that we are doing everything in our power to resume these critical works as soon as possible.

“However, given the delay, we do not anticipate completion by the previously stated date of September 3.”

The harbour wall after it collapsed in 2017.

Harbour historian fears its time could be up

The harbour dates back to 1625 and about 30 small boats still fish out of it almost 400 years later, though most berths are occupied by pleasure crafts.

One of the harbour users, Phil Hemsley, told us how he craned his yacht from the water earlier this year to keep it at Lossiemouth.

But many others crafts remain trapped, unable to leave while sections are enclosed by large bunds to enable the construction work.

Many boats are unable to leave. Picture by Paul Glendell

Phil, something of a local historian when it comes to the port, has grave fears about its future if work doesn’t resume urgently.

He said: “Something wants doing before the winter gales come, that’s the most important thing.

“Otherwise, Banff Harbour could be finished.

“The people of Banff, many years ago, invested in that harbour and when the council took it over they inherited the responsibility of keeping it going.”

Temporary repairs were put in place to shore up the damaged jetty before the £1.3m project began

Chairman of the Banff Harbour Advisory Committee, councillor John Cox, echoed those concerns.

Mr Cox said: “I recognise that the way the harbour has been left, with half of the pier taken away, could be a significant concern if there was a combination of high tides and bad weather.

“I can see that being an issue, we have to ensure that doesn’t happen.

“That would be devastating.”

Lochshell’s website states that the firm has 40 years of experience in engineering, construction and steel fabrication.

Previous clients include Moray Council and Highland Council.

Key part of £350m harbour expansion ‘may not be viable’ as bosses reveal they have received no Covid-19 support