Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

“Loose cannon” Willie Young blasted by Aberdeen MSP

Is Cllr Young a "loose cannon"?
Is Cllr Young a "loose cannon"?

A furious row broke out last night after Aberdeen City Council’s finance chief accused the Scottish Government of stealing workers from a key infrastructure project.

Councillor Willie Young wrote online that the reason behind the recently announced seven-week delay to the Third Don crossing was because Holyrood “stole all the contractors to deal with the AWPR”.

But last night an angry city MSP hit back at Mr Young – who has an active social media account – and described him as a “loose cannon” who was “deflecting attention from himself and administration”.

The row broke out on day it emerged council bosses – including chief executive Angela Scott and leader Jenny Laing – are being hauled before a Holyrood committee, after the authority was accused of snubbing a meeting yesterday.

And although Mr Young often has online spats with political opponents, and protesters against the controversial Marischal Square project this latest rant was directed at the Scottish Government.

It erupted after the Bridge of Don councillor was asked on Twitter why the £18million Don crossing was being delayed by seven weeks.

He responded: “Scottish Government’s fault, they stole all the contractors to deal with the AWPR, hope that helps”.

Willie Young post on Twitter
Willie Young post on Twitter

The council announced the delay on Tuesday, and blamed difficulties rerouting underground utilities.

Last night furious Aberdeen Donside MSP Mark McDonald suggested the message was a way of deflecting attention, and insisted it would not “make sense” for workers to be moved around on the joint projects.

He said: “The idea that the government are pinching workers from the crossing for the AWPR is total nonsense.

“It would effectively mean that the council were pinching their own workers.

“We can see this is another fictional scenario created by Councillor Young in a desperate attempt to deflect attention from himself and his administration.”

Speaking last night, Mr Young clarified that although his Tweet referred to contractors, he intended to refer to utility companies who are having their resources split between the two projects.

He also blamed confusion on the number of letters allowed per post on the social media platform.

He said: “You’ve got to read the Tweet in context. You’ve only got 140 characters.”

The finance convener also defended his position of “all the contractors” being “stolen” by the Scottish Government, despite Transport Scotland not confirming the full extent of utility diversions.

Mr Young added: “From my point of view, ‘all’ means that all of the people we had have been moved across to the AWPR.

“It depends on your interpretation of ‘all’, but my interpretation of ‘all’ is at that particular time everybody moved from our contract to their contract.

“We’ve got two major projects in the city. One is the AWPR, and one is the Third Don Crossing.

“They want to move the AWPR on as quick as they can, which means there will be a delay at the Third Don Crossing. It’s not a criticism, it’s just a fact of reality.

“They’re got their knickers in a twist for nothing.”

A Transport Scotland spokesman last night said a large number of utilities are currently being re-routed towards the AWPR project.

The spokesman said: “There are a significant number of utility diversions underway on the AWPR/Balmedie to Tipperty project.

“Following liaison with the contractor, utility companies determine the appropriate level of resources for the project.

“A regular forum has been established with the utility companies to allow the planning and co-ordination of the AWPR/Balmedie to Tipperty diversion works.”