Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

West Highland Line to reopen on Monday

Where the rail line has been left exposed after a landslip.
Where the rail line has been left exposed after a landslip.

A major Highland rail line will reopen on Monday after major repairs were completed ahead of schedule.

The West Highland Line was closed on Sunday, August 4 after heavy rain battered the country, causing sections of ballast and embankment to be washed away and submerged by landslips.

Further severe weather a week later caused parts of the line to be blocked by debris at Arrochar.

Since the line closure, Network Rail teams have worked on the damaged sites – strengthening embankments and rebuilding the track bed before reinstating the railway.

More than 3,000 tonnes of rock, including 350 one-tonne rock armour blocks, was delivered to the site and used to rebuild and support the embankments.

Transport secretary Michael Matheson said:”I want to thank the workforce who have put in a tremendous effort to get this work complete.

“Their dedication and commitment to getting these repairs carried out has ensured that the line has been completed early to get passenger services re-established.”

Alex Hynes, managing director of Scotland’s Railway said: “This was a very complex series of repairs, because we needed to reconstruct the slope beneath the line – replacing thousands of tonnes of lost material – before repairing the tracks above.

“It was made even more challenging by the remote location, but our teams have worked superbly well to get the job done safely.”

The site south of Crianlarich is the last section of the line to complete repairs with sections north of Crianlarich to Oban re-opening on Monday, August 12 and a landslip at Arrochar, to the south, cleared and the line re-opened on Thursday, August 15.