Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Finish date for Anderson High School pushed back to April 2017

The plans unveiled for the new Anderson High School which were meant to be finished in 2016
The plans unveiled for the new Anderson High School which were meant to be finished in 2016

The projected finish date for the new £42million Anderson High School and halls of residence in Lerwick has been pushed back to April 2017.

It had been expected for several months that the previous completion date of summer 2016 would no longer be achievable.

Last month, a leaked document suggested the building would not be open until spring 2017, and that was officially confirmed by Shetland Islands Council yesterday.

During a press briefing in Lerwick town hall, head of schools Helen Budge said she was “confident” the new completion could be met.

She also said that the project continued to be on budget although the exact cost would only be known at ‘financial close’ in March next year when prices for all elements of the massive projects have been received.

Shetland Islands Council has already earmarked £14 million as its contribution to the project with the remaining two thirds coming from the Scottish Government.

Described by education committee chairwoman Vaila Wishart as a “like for like replacement” the new school will have 39 classroom, 12 science laboratories, art studios, music and home economics classrooms, a library and an assembly hall.

Once completed, the local authority will save hundred of thousands pounds in maintenance costs to the existing Anderson High School.

The project team is currently working on finalising the internal layout of the new school, which will now be a timber-cladded four-storey building.

The new halls of residence at Lower Staneyhill will have 100 bed spaces with en-suite facilities in all bedrooms.

Ms Budge said the delay was mainly due to the 26 planning conditions imposed on the project as well as the fact that main contractor Miller Construction had recently been taken over by rival Galliford Try plc.

“There has been some time over the summer when the project wasn’t progressing in the same way it now is,” she said.

She added: “From our point of view we are delighted to get planning permission and we will work through those condition and make sure we meet them all.”

With building work planned to commence in April 2015, Ms Budge said she was confident the school could be built in the two-year slot even with allowing for delays due to the Shetland weather.