Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Another blow dealt to much-delayed construction project for new Moray primary school

Nearly 500 pupils will be able to attend Linkwood Primary School in the south of Elgin
Nearly 500 pupils will be able to attend Linkwood Primary School in the south of Elgin

A fresh blow has been dealt to a troubled project to build a new school in Moray.

Linkwood Primary School was originally due to welcome its first pupils in the south of Elgin after the summer holidays last year.

However, construction is yet to begin on the complex, which will have space for 450 pupils to ease the pressure on the town’s classrooms.

Now it has been revealed that mechanical and electrical installation firm Richard Irvin, which fell into administration in December, was one of the contractors due to work on the school.

Moray Council has warned the development has the potential to increase the cost and delay the £12.8million project yet again.


>> Keep up to date with the latest news with The P&J newsletter


The plans are already more than £1million over budget after being hit by two years of delays due to issues including a wrangle over the ownership of the land, which is being delivered as part of a wider Springfield Properties development.

The council expects final documentation to transfer the site to its ownership to be received to allow construction to finally begin before the end of the month.

But Elgin City South councillor John Divers believes lessons need to be learned for future projects to stop similar hold-ups from happening again.

He said: “Whenever there are delays it can lead to a price rise, whether that’s due to an increase in cost of materials, extra staff or whatever.

“There’s been a number of unusual issues with this one and as with any major construction project there will be room to learn from that.”

Pupils due to attend Linkwood Primary School are currently being taught in temporary classrooms at East End Primary School.

Opening of new Moray primary school could be pushed back to 2020 as the cost soars £1m over budget

The new buildings are due to be ready in summer 2020 but the council has warned the deadline remains a “significant risk”.

Councillors are due to meet on Wednesday to receive an update about the project.

In a report, Nick Goodchild, the authority’s educational resources manager, said: “On December 24 notification was received that the mechanical and electrical contractor appointed to the project had gone into administration.

“Hub North and Balfour Beatty are in negotiation with other contractors and are very aware that no additional funding is available. This circumstance however, has the potential to impact on the cost and timeframe of the project.”