Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

North motorists face disruption for the next eight weeks on only completed section of A9 dualling programme

Previous roadworks on the A9 between Kincraig and Dalraddy during the construction of the dual carriageway
Previous roadworks on the A9 between Kincraig and Dalraddy during the construction of the dual carriageway

Motorists in the Highlands are facing another eight weeks of traffic restrictions on the only completed section of the A9 dualling programme.

Half of the five-mile Kincraig to Dalraddy road will be restricted both ways to a single lane and 50mph speed limit for six weeks, with the whole route being affected for a two further weeks.

Average speed cameras will also be in use.

Highland MSP casts doubt on official explanation for A9 work hold-up

Work began last night to lay fibre optic cabling – known as Intelligent Transport Systems (ITS) – along the verges to connect with roadside electronic message boards along the busy trunk road.

It comes just months after the stretch fully reopened following two years of dualling works.

Badenoch and Strathspey councillor Bill Lobban described the decision to do the work during the busy tourist season as “ludicrous” and was astounded by what he says has been a lack of consultation on the timing of these works.

He added: “This will go down very badly with the public.

“We all appreciate these works have to be done, but why do them in the middle of summer? Why not in the spring or autumn when there are fewer cars and fewer tourists?

“I would suggest the sensible thing to do in future would be to do these works during the dualling work, and to do it outwith the busy period when it’s not inconvenient for drivers.”

The spokesman for the national transport agency said the ITS network was not installed in September, when the new dual carriageway opened, as it was “not critical” to its operation and it was decided to complete the works at a later date to prevent further delay to the road’s opening.

He acknowledged that, while the works could have been carried out during winter months, the poorer weather and conditions, coupled with the works happening close to the main road, would have “compromised safe working practices.”

And the spokesman said shorter days would be less productive, resulting in restrictions for a longer period and increasing disruption.

But Mr Loban said these explanations were inadequate and reiterated his doubts over the Scottish Government’s estimated 2025 completion date for the £3billion dualling programme.

Only the Kincraig to Dalraddy section has been finished so far, which represents just 6% of the 80 miles to be dualled.

Construction is due to start on another section between Luncarty and Pass of Birnam in the coming months.

Transport Scotland previously said that many of the other dualling sections are being progressed simultaneously, allowing the 2025 date to be achieved.

It is also understood that, during the eight weeks of works between Kincraig and Dalraddy, average speed cameras will be operating on parts of the road subject to the restricted 50mph speed limit.

A 40mph speed limit was put in place and traffic was restricted to one lane in both directions when work started to dual the five-mile stretch in September 2015.

A freedom of information request by The Press and Journal revealed that more than 1,800 motorists were caught speeding through the 40mph roadworks in the first three months for which data was available, with another 2,000 caught in the subsequent three months.

It is expected that the new traffic management measures will be in place on the A9 from Kincraig to Dalraddy until about August 3.

Information about the works have been communicated in the form of road-side signs, travel bulletins, and by Transport Scotland on social media.