Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Moray Council object to wind farm plans amid fears about effect on landscape

Clash Gour windfarm
Clash Gour windfarm

Councillors have objected to plans for a large wind farm near Moray.

Force 9 Energy want to build the Clashgour wind farm, consisting of 48 turbines, about seven miles south of Forres.

Their plans have been lodged with the Scottish Government but yesterday, local councillors got to have their say and rejected the scheme – meaning a local public inquiry must now be held.

The turbines would almost completely encircle the existing Berry Burn site, although the turbines would be about 75% larger, standing between 425ft to 575ft.

In a report, Moray Council’s planning team said the project would cause “unacceptable” damage to the landscape by creating a wave of interconnected wind farms between Hill of Glaschyle, Berry Burn and Paul’s Hill which would be almost impossible to tell apart.

And at committee yesterday, councillors seized on those concerns and claimed they would be overlooked by the Scottish Government.

Councillor George Alexander said: “Advice has been given out consistently to the applicant that the turbines were against our policies and officers identified five different policies that were breached.

“Why is it that the applicant has chosen to ignore these policies, is it because they believe that even if we reject it, the Scottish Government will approve it?

“All this work we do is just brushed aside and a higher authority will decide so why have they ignored our concerns?”


>> Keep up to date with the latest news with The P&J newsletter


Principal planning officer Neal McPherson suggested the policy was open to interpretation.

He said: “They take a different view and interpretation of our policy along with the national policy guidance and take a balanced view that the application would be accepted.”

Councillors were given the chance to object to the proposals fully or recommend a secondary option, for smaller turbines to be installed instead.

Paula Coy

Elgin City North councillor Paula Coy put forward the second option as she does not believe the overall development would create a “wind farm landscape” and that they would not have an “accumulated impact” on the area.

However, that motion was defeated seven votes to three, meaning the council has officially objected to the scheme.

Andrew Smith, head of planning and development at Force 9 was “disappointed” but vowed to continue to work with the local community to seek a solution.

He said: “We are naturally disappointed by Moray Council’s decision to object to the Clash Gour Wind Farm proposal, especially given the level of support we have seen from community groups across Moray regarding the shared ownership opportunity associated with the proposals and also the estimated £26.7 million that would be added to the Moray economy from the project.”

“We fully believe that the proposal, which incorporates stakeholder feedback together with the significant environmental and technical survey work undertaken, strikes the right balance by minimising and mitigating environmental effects, whilst at the same time maximising the economic benefits and opportunities for Moray.

“We will continue to work with community groups across Moray to seek to realise the community shared ownership opportunity which unfortunately will now face a lengthy delay in coming forward, given the council’s objection to the wind farm and the public inquiry process that will now occur.’’