Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Campaigners outraged power line plan that will dwarf local landmark is approved

Dufftown business owner Alistair Jeffs is concerned the power lines will be taller than the Dufftown clock tower.
Dufftown business owner Alistair Jeffs is concerned the power lines will be taller than the Dufftown clock tower.

The Scottish Government has approved a controversial power line project – prompting fury from campaigners who wanted to protect the countryside.

Scottish and Southern Energy Networks (SSEN) have been given the go-ahead to hook the Dorenell windfarm near Dufftown to the national grid with a 14-mile stretch of poles.

But outraged locals called for the cables to be put underground to preserve the natural beauty of Speyside’s moorland.

Last night they were dismayed at the Scottish Government’s decision to back the scheme, and claimed the energy firm’s consultation had been a “tick box exercise”.

Up to 135 poles that are 78ft tall will now be dropped into location by helicopter as part of the project that will stretch from Blackhillock near Keith to the 59 wind turbines.

SSEN has insisted they have included measures designed to reduce the impact on the natural environment, and said last night they would now be preparing for the construction phase.

Dufftown bed and breakfast owner Alistair Jeffs said: “We’re devastated. Some months ago about 30 of us had a meeting with the firm to talk about our concerns. They promised to consider them and report back – they never have.

“It’s the same old story, it’s just a tick box exercise. They can say they’ve come to see us and taken our views into account but they haven’t.

“People come here for the scenery – the drive from Dufftown to Huntly is stunning. It’s just becoming more and more covered with pylons and turbines though.

“They say they can’t put the cables underground because it’s too costly but they won’t give the costs though.”

Throughout the process SSEN has insisted they cannot put the cables underground because they are obligated to deliver best-value for the publicly-funded scheme.

Moray Council’s planning committee refused to back the proposals amid calls more consideration should be given to bury the power line out of sight.

The plans also attracted opposition from Forestry Commission Scotland after it was revealed 163 acres of ancient trees would be chopped down. The power firm later offered to replant the felled woodland.

Colin Mackenzie, who lives near the 15th century Auchindoun Castle, submitted a 26-page objection document after

learning the cables would pass within a mile from the landmark.

He said: “The principal reason for tourists to come to this area are whisky, castles and landscape. Dufftown’s commerce and economy is heavily dependent on them.

“To allow two out of the three of these to be degraded would be working directly against the efforts going in nationally and locally.

“How disappointing will it be for future visitors to have to follow the transmission line up the glen and through the Ballach gateway into the Cabrach?”

In their findings, Scottish Government planners concluded the impact on the environment was outweighed by the benefits of the power line once mitigation measures were considered.

Paul Higginbotham, SSEN’s lead project manager, said: “In our application for consent we identified and committed to environmental mitigation such as compensatory woodland planting and a detailed environmental management plan which

will ensure construction impacts are minimised.

“We will now prepare for the construction phase and are fully committed to keeping the local community and other interested parties updated as the project progresses.”