Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Orkney councillors turn down request for more time to build wind farm

Orkney councillors have turned down a request for more time to start building the turbines at Costa Head, Birsay.
Orkney councillors have turned down a request for more time to start building the turbines at Costa Head, Birsay.

Orkney council’s planning committee have turned down an application from a wind farm developer asking for more time to get started on one of their projects.

Planning permission for Edinburgh-based Hoolan Energy’s four-turbine development at Costa Head, Birsay, will expire this April.

The developer had initially asked the council for five years to be added on to the three-year time limit they had to begin building the project.

They had also asked for five years to be added on to a 25-year time limit to have the project up and running.

However, this is not what was considered by the planning committee.

Instead, they considered extending the three-year limit to 10 years and keeping the 25-year limit as it is.

The council said these changes would fall in line with recent wind farm decisions made by Scottish Ministers.

In particular, with the recent decisions made on applications the council put to the government for its own wind farm projects in Hoy and Quanterness.

Hoolan’s turbine proposals for Costa were turned down by the council’s planning committee in August 2018.

However, this decision was overturned in April 2019, after an appeal was made to the Scottish Government.

The same transpired for another Hoolan project at Hesta Head, in South Ronaldsay.

Council changed recommendation based on government’s decision on Hoy and Quanterness wind farms

Despite the Scottish Government being the body that gave the projects the thumbs up, it fell to Orkney council’s planning committee to decide whether to give the developer more time.

Councillor Owen Tierney said it was “kind of funny” that the committee was being asked to approve the extension on a condition they refused in the first place.

The development director with Hoolan, Lizzie Foot explained their position.

She said the Costa Head turbines would provide a significant contribution to the needs case for the new interconnector between Orkney and the Scottish Mainland.

However, she said the Costa project has been “absorbing grid connection delays” around the interconnector and a grid offer connection is expected to be delayed once again.

The planning committee heard from three objectors at the meeting.

Jason Scholfield and Jim Leitch, who are both Evie residents, spoke and had a letter read out, respectively.

Objector says developer has had ample time to get started

Mr Leitch said the applicant had had “ample time” to build their wind farm.

Noting that with Orkney council entering into the commercial wind farm business, he said he sees the council and Hoolan Energy as commercial businesses with “a common goal” in getting permission for a new interconnector to mainland Scotland approved.

There were also concerns about the project’s effect on peregrine populations.

A letter of objection from the RSPB was also read out. The organisation said it was concerned by the council considering giving Hoolan 10 years to build when it had only asked for five more.

The RSPB said data could be up to 15 years old by the time the turbines are up and this could invalidate the environmental assessment.

Councillor John Ross Scott moved to approve the application but there was no seconder.

The committee’s chairman Rob Crichton then moved to refuse.

He said: “I chaired the meeting where the original decision was to recommend for refusal.

“I took the Scottish Ministers reporters at true value and I’m happy with the conditions that were put on it. I don’t feel there’s been proper justification as to why things should have changed.”

A similar application for Hoolan Energy’s Hesta Head development is still awaiting a decision from the council.